Bitterroot Nutrient TMDL Schedule

This version was saved 14 years ago View current version     Page history
Saved by Christina Staten
on April 14, 2010 at 5:41:01 pm
 

Schedule for Development of the Bitterroot Nutrient TMDLs

 

The table below displays the projected time periods for major tasks in the development of the Bitterroot Mainstem Nutrient TMDLs. The status of each task is displayed as either:

Not Started

In Progress

Completed

Delayed

The table will be updated if there are project delays resulting in significant changes to the task start and end dates. The original dates will be struck through, and new dates will be posted beneath. You may download a PDF of the Microsoft Project document to see the complete, detailed project schedule. Click on the Adobe icon below if you need to download the free software needed to view the document. For questions regarding schedule tasks or dates, please contact Darrin Kron, DEQ Nutrient Project Manager at 406-444-4765.

 

 

 

Main Tasks Subtasks Start Date End Date Status
Data Gathering  

1/1

2010

12/13

2010

 In Progress 

  Compile Existing Data    

 

  Collect Data (summer 2010 tributary nutrient sampling)      
  Complete Summary of Gathered Data      
     
SWAT Modeling  

1/1

2010

2/11

2011

In

Progress 

  Development of Nutrient Source Reports      
  Development of Model QAPP (Quality Assurance Project Plan) by DEQ Modeler      
  Calibration of SWAT Model by DEQ Modeler      
  DEQ Project Manager Review of Model Calibration      
  Analysis of Model Scenarios      
  Development of Model Scenario Results Report by DEQ Modeler      
  DEQ Project Manager Review of Model Scenario Results      
  TAG Review of Model Results

1/17

2011

2/11

2011

 
     
Write Up of Nutrient Document Section  

11/13

2010

4/29

2011

Not Started
  Development of Targets to Evaluate Existing Stream Conditions      
  Analysis of Existing Stream Conditions

 

 

 
  Analysis of Nutrient Source Contributions      
  Development of the TMDLs, Allocations, & Margins of Safety      
     
Write Up of Initial & Latter Document Sections  

4/25

2011

6/10

2011

Not Started

 

Introduction

Watershed Description

Description of MT Water Quality Standards

Restoration Objectives / Implementation

Monitoring Effectiveness

     
     
WAG / TAG Document Review & Meeting   

5/16

2011

6/10

2011

Not Started 

 

Public Review & Response  

6/13

2011

10/24

2011

Not Started
  Project Manager Review & Consideration of Stakeholder Comments      
  Format & Publish Public Document      
  Public Comment Period      
  Conduct Public Meeting      
  Address Public Comments      
  Format & Publish EPA Submittal Document      
Projected Date of Document Submission to EPA  

 

11/2

2011

 

 

BACK TO THE BITTERROOT PROJECT OVERVIEW & CONTACTS PAGE 

 

Go to the Sediment & Temperature TMDL Schedule Page

 

Page Released: April 14, 2010

Last Updated: Never