Bitterroot Nutrient TMDL Schedule

This version was saved 13 years, 2 months ago View current version     Page history
Saved by Christina Staten
on January 25, 2011 at 3:44:06 pm
 

Schedule for Development of the Bitterroot Nutrient TMDLs

 

The table below displays the projected time periods for major tasks in the development of the Bitterroot Mainstem Nutrient TMDLs. The status of each task is displayed as either:

Not Started

In Progress

Completed

Delayed

The table will be updated if there are project delays resulting in significant changes to the task start and end dates. The original dates will be struck through, and new dates will be posted beneath. You may download a PDF of the Microsoft Project document to see the complete, detailed project schedule. Click on the Adobe icon below if you need to download the free software needed to view the document. For questions regarding schedule tasks or dates, please contact Darrin Kron, DEQ Nutrient Project Manager at 406-444-4765.

 

 

 

The temperature and tributary sediment TMDLs will be completed under a separate document. To see this completion schedule, please go to the Bitterroot Sediment and Temperature TMDL Schedule page. 

Main Tasks Subtasks Start Date End Date Status
Data Gathering  

Jan 2010

1st quarter  2011

 In Progress 

  Compile Existing Data    

 

  Collect Data (summer 2010 tributary nutrient sampling)      
  Complete Summary of Gathered Data      
     
SWAT Modeling  

Jan

2010

2nd quarter

2011

In

Progress 

  Develop Nutrient Source Reports      
  Calibrate SWAT Model      
  Analyze Model Scenarios      
  Develop Model Scenario Results Report      
  TAG Review of Model Results

TBD

TBD

 
     
Write Up of Nutrient Document Section  

2nd or 3rd quarter 2011

3rd or 4th quarter

2011

Not Started
  Develop Targets to Evaluate Existing Stream Conditions      
  Analyze Existing Stream Conditions

 

 

 
  Analyze Nutrient Source Contributions      
  Develop the TMDLs & Allocations      
         

 

Draft Document Development & Formatting       Not Started
  WAG & TAG Review of Draft Document Estimated 4th quarter 2011    
  DEQ Review & Consideration of Stakeholder Comments      
  Format & Publish Final, Draft Document for Public Comment      
         
Public Review & Publishing of Final Document       Not Started
  Public Comment Period TBD  TBD   
  Public Meeting      
  DEQ Review & Response to Public Comments      
  Format & Publish Final Document for Submittal to EPA      
Projected Date of Document Submission to EPA  

 

Estimated 1st quarter 2012

 

 

BACK TO THE BITTERROOT PROJECT OVERVIEW & CONTACTS PAGE 

 

Go to the Sediment & Temperature TMDL Schedule Page

 

Page Released: April 14, 2010

Last Updated: January 25, 2011 (dates updated)